Remodeling Schedules Can Be Tricky
Posted October 28th, 2008 by tinaWe’re getting close to wrapping up the Newburyport condo remodel. It’s tricky orchestrating all the pieces. As I needed to write them down, I thought I’d share the planning and hopefully help someone out there. Our customer’s goal is to wrap up phase 1 asap - bathrooms, flooring and a deep clean.
We couldn’t buy the stair pie treads pre-finished from the same manufacturer, so we decided to finish all the steps the same way.
Left to complete (yes, the punchlist is a little longer offline):
- Grout the bathroom walls.
- Install vanity - sink, counter top and faucet arrive today.
- Paint the master bath - colors approved this morning.
- Install the remaining light fixtures that were ordered on the web.
- Re-finish the wood floors on the first floor - worn in dining area.
- Stain/finish stairs - just picked up the pie treads yesterday.
- Paint the new risers.
- Install neo-angle shower door when it arrives.
When all done, a deep cleaning to get rid of all the dust from the work just completed. Then onto painting and furnishing the condo.